EN

THE CASTING OF THE 13TH FLOOR SLAB HAS BEEN COMPLETED

24 July, 2026

THE CASTING OF THE 13TH FLOOR SLAB HAS BEEN COMPLETED

Construction is progressing fully on schedule!

 

Completed so far:
▪️ 2-level underground parking;
▪️ 2 commercial floors;
▪️ 11 residential floors;
▪️ Internal partition walls completed on 6 residential floors.

 

The project features:
◾ 4,500 sq.m of private, secure courtyard;
◾ 2-level underground parking;
◾ Children's playgrounds and recreation areas;
◾ 3.1 m ceiling height in the apartments;
◾ Commercial and office spaces;
◾ 400 m from Samgori Metro Station.

Construction will be completed by the end of 2027.